To see a map of the scheduled dates for the road closure on 18th Street click the link below.
    
Culvert replacement map.pdf

http://mdotnetpublic.state.mi.us/drive/Default.aspx

2017 Michigan Road Repair Projects

Click here for Allegan County Roads Closures

The reconstruction of 18th Street from 142nd to 144th Avenue will not occur until the spring/summer of 2018. During the same period of time the north three miles of 18th Street from 144th to the Kent County Line will be resurfaced.

 

The County may need to do some culvert replacement in 2017 in preparation for the 2018 project. They will set up their message boards to make people aware of the culvert replacement schedule about 1 week ahead of the closure.

 

The County anticipates a public meeting will be held in the Fall/winter of 2017 regarding the reconstruction project scheduled for 2018. The project went out to a consultant for design this month.

 

 

Road Construction on 144th Ave
Between 14th and 17th St
Now thru mid-November
Follow Detours -or- Seek Alt. Route